R&D tax credit material costs: the 20 % overhead allowance from 2026

Materials, equipment and licences are not a separate cost category under the FZulG. They enter the assessment basis (Bemessungsgrundlage) only two ways: depreciation on certain capital assets, and for new projects, the 20 % flat rate.

  • Material costs are not their own cost category (§ 3 FZulG)
  • Depreciation on capital assets from fiscal year 2024 (§ 3 (3a))
  • 20 % flat rate for projects from 2026 (§ 3 (3b))
At a glance

Equipment in your research project

Equipment in your research project — Document use and depreciation
Document use and depreciation
Figures and details
Personnel costs count in full, capital assets only via depreciation, materials not directly
Cost types of an R&D project (example)EUR 1,000,000Personnel costs and contract research(§ 3 (1), (4))EUR 700,000Depreciation on capital assets, onlythe AfA (§ 3 (3a))EUR 100,000Materials, licences, rent – notdirectly eligibleEUR 200,000Materials, licences and rent are not their own cost category. For projects started after 31December 2025, the 20% flat rate covers part of them indirectly (§ 3 (3b) FZulG);depreciation under § 3 (3a) remains a separate case.

Key facts in brief

Material costs are not a separate cost category under the FZulG: materials, consumables, licences, travel costs and rent cannot be claimed directly. Eligible are wages (§ 3 (1) FZulG), own contributions by sole proprietors and partners (§ 3 (3)) and 70 % of contract research (§ 3 (4)). Since the Growth Opportunities Act, depreciation on certain movable capital assets acquired after 27 March 2024 has also been eligible (§ 3 (3a)). For projects starting after 31 December 2025, a 20 % flat rate on the eligible expenses under § 3 (1), (2), (3), (3a) and (4) additionally covers further overhead and operating costs on a lump-sum basis (§ 3 (3b)).

The essentials on material costs

  • Directly eligible
    Wages (§ 3 (1)), own contributions (§ 3 (3)), 70 % of contract research (§ 3 (4))
  • Eligible via depreciation
    Depreciation on movable capital assets acquired after 27 March 2024 and used in the project (§ 3 (3a))
  • Covered by the flat rate
    20 % on personnel costs, own contributions and the eligible contract research share, only if the project started after 31 December 2025 (§ 3 (3b))
  • Not eligible
    Materials, software licences, travel costs and rent as individual items
  • Funding rate
    25 %, 35 % for SMEs
  • Cap
    at most EUR 12 million assessment basis per year (from 2026)
  • How do material costs enter funding via the flat rate from 2026?

    Through a flat 20 % surcharge on the total eligible expenditure from personnel costs, own contributions, depreciation and the eligible contract research share – with no individual proof of actual overhead costs required (§ 3 (3b) FZulG).

    How the 20 % flat rate is calculated: from personnel costs to the assessment basis
    R&D personnel costs(employer gross)EUR 500,000Overhead flat rate 20 %EUR 100,000Assessment basisEUR 600,000Funding rate 25 %EUR 150,000

    Example: EUR 500,000 in personnel costs, no contract research, project started after 31 December 2025 (§ 3 (3b) FZulG). The flat rate is added automatically, with no individual proof of material costs.

    Types of material costs: direct, via the flat rate, or not at all
    Cost typeCounts directly?Legal basis
    MaterialsNo, only via the flat rate, if the project started after 31 December 2025§ 3 (3b)
    ConsumablesNo, only via the flat rate, if the project started after 31 December 2025§ 3 (3b)
    Prototype buildingNo, as consumable material only via the flat rate; if the prototype becomes a movable fixed asset, depreciation applies instead§ 3 (3b)
    Software licencesNo, an intangible asset, only captured via the flat rate§ 3 (3b)
    RentNo, only via the flat rate, if the project started after 31 December 2025§ 3 (3b)
    EnergyNo, only via the flat rate, if the project started after 31 December 2025§ 3 (3b)
    Depreciation on movable capital assetsPartly: only the annual depreciation, independent of the flat rate, if the asset was acquired after 27 March 2024 and used in the project§ 3 (3a)

    Are material costs eligible?

    No, not as a separate cost category, because the FZulG does not recognise materials, licences or rent as part of the assessment basis. They enter only two ways: depreciation or the overhead flat rate, as the overview further above shows for each cost type.

    § 3 FZulG lists exhaustively what may enter the assessment basis: wages, own contributions by sole proprietors and partners, contract research, depreciation on certain capital assets and, for new projects, the overhead flat rate. Material costs are not on this list.

    • Via depreciation (§ 3 (3a)): only the annual depreciation on movable capital assets, acquired after 27 March 2024 and used in the project.
    • Via the overhead flat rate (§ 3 (3b)): 20 % on personnel costs, own contributions and the eligible contract research share, only for projects started after 31 December 2025.
    Common misconception: the flat rate is not a substitute for proof of material costs. It is calculated from personnel costs, own contributions and contract research, not from actual material or licence spending. Companies with little staff but high material costs barely benefit.

    Which cost type belongs where?

    The line runs not between cost types but between whose work it is: an employee's time, a capitalised asset, or a genuine contract research agreement.

    Common edge cases for material costs
    CaseClassificationLegal basis
    Software: bought or built in-house?A purchased licence does not count directly, only via the flat rate. The time of your own developers counts as personnel costs instead, regardless of the fact that software is the result.§ 3 (1), (3b)
    Prototype: consumed or capitalised?If the company consumes the prototype or does not capitalise it, it counts as material only via the flat rate. If it capitalises it as a movable fixed asset, the annual depreciation counts, provided it was acquired or produced after 27 March 2024.§ 3 (3a), (3b)
    Outside service or contract research?Only contract research counts, then at 70 % of the fee. An outside service that is not contract research is not on the exhaustive list of § 3 FZulG and does not count.§ 3 (4)
    The line is drawn by the contract and the accounting, not by the word on the invoice: the same expense can be personnel costs, depreciation, or nothing at all, depending on who performed it and whether it is capitalised.