Research Allowance for contract research: 70% count, 30% don't

Commission a contractor in the EEA after 27 March 2024 for R&D work, and 70% of the fee counts toward the assessment basis. Before the additional flat rate, this equals 17.5% of the fee, or 24.5% for SMEs. We review the contract and invoice before the application goes out.

  • 70% of the fee is eligible, for contracts placed after 27 March 2024
  • The contractor must be based in the EEA
  • From 2026: an additional 20% overhead flat rate
At a glance

Research across company boundaries

Research across company boundaries — Client and research partnerContractResearch
Client and research partner
Figures and details
70 percent of a contract handed to a third party count
Contract researchEUR 500,00070 % eligible (§ 3 (4) FZulG)EUR 350,00030 % do not countEUR 150,000

Example: EUR 500,000 in contract fees, for contracts placed after 27 March 2024. From 2026, the 20% overhead flat rate additionally applies to new projects on the eligible share (§ 3 (3b) FZulG).

Key facts in brief

Contract research (Auftragsforschung) exists when a company (the client) commissions an external contractor in the EEA for R&D work. The client claims 70% of the fee as the assessment basis (Section 3(4) FZulG), for contracts placed after 27 March 2024; before that the rate was 60%. From 2026, a 20% overhead flat rate applies to projects started after 31 December 2025, and it also applies to this 70% share (Section 3(3b) FZulG). Only the client can claim the allowance; the contractor may not additionally claim the same costs as its own R&D.

The essentials of contract research

  • Eligible share of contract fee
    70% of the fee, for contracts placed after 27 March 2024 (60% before)
  • Overhead flat rate
    an additional 20% on the 70% share, only for projects started after 31 December 2025
  • Funding rate on the assessment basis
    25%, for SMEs 35%
  • Share of fee before the flat rate
    17.5%, or 24.5% for SMEs (contracts after 27 March 2024)
  • EEA requirement
    the contractor must be based in the European Economic Area
  • Cap
    EUR 12 million assessment basis per year, EUR 10 million before
  • Who can claim
    only the client; the contractor may not additionally claim the same costs
  • What is contract research under Section 2(4) FZulG?

    Contract research exists when a company (the client) commissions an external contractor for R&D work. Only the client can claim the allowance for it.

    The contractor can be a university, a research institute, an engineering firm, or another company. What matters is not the legal form but whether the service has R&D character and the contractor is based in the EEA.

    Three categories, three assessment bases

    • In-house research: own staff, own resources. Eligible are the employer gross wages of R&D staff, plus the 20% overhead flat rate from 2026.
    • Contract research: an external contractor in the EEA carries out the R&D work. 70% of the contract fee counts toward the assessment basis.
    • Cooperative research: equal partners research jointly. Each partner claims the allowance only for its own personnel costs; offsetting the partner's costs is excluded.
    Contract research compared with cooperative research
    CriterionContract researchCooperative research
    Who claimsOnly the clientEach partner for its own costs
    IP rightsWith the clientShared by agreement
    Eligible costs70% of the feeOwn personnel costs
    EEA requirementContractor must be in the EEANo restriction

    Typical contractors are universities, Fraunhofer Institutes, Helmholtz and Leibniz Centres, and specialised engineering firms. What matters in every case is the R&D character of the service, not the name of the institution.

    In practice, many companies combine in-house research and contract research: own staff work on part of the project, and an external institute handles another part. Both assessment bases add up to one total, capped at EUR 12 million per year.

    If both the client and the contractor claim the same costs, this is impermissible double funding. The tax office reclaims it during an audit, with interest.